References

Finished Projects

ARTVİN DAM & HPP: 332 MW, Artvin - Turkey | 2018

Employer: General Electric Renewable Energy | Investor: Doğuş Enerji

OPERATIONS: Supervision

GEMKÖPRÜ HPP: 1,9 MW, Malatya - Turkey | 2018

Employer: Kıvanç Enerji | Investor: Kıvanç Tekstil Enerji

OPERATIONS: Supervision

• The turbine snails of the two units were placed and tested penstock

KOCAMAN HPP: 1x3,3 MW, Artvin - Turkey | 2018

Employer: Mim Yapı | Investor: Kocaman Enerji

OPERATIONS: Installation / Supervision

• Completion of Electro-Mechanical Installation of 1xYatay Axis Pelton Type Turbine and Generator at 1x3.3MWe Power,
• Supervision,
• Commissioning and on-site delivery

OKKAYASI REGULATOR AND ŞEHİTLİK HPP: 23 MW, Kahramanmaraş - Turkey | 2018

Employer: Andritz France | Investor: Okkayası Elektrik Üretim

OPERATIONS: Intervention

• Change of the Unit 2 Nozzle 1,2 and 3 seals and nozzle 1 tip.

ÇAYALTI REGULATOR AND HPP: 11 MW, Zonguldak - Turkey | 2018

Employer: Andritz France | Investor: Reis Grubu

OPERATIONS: Intervention

• Çayaltı 2 Unit 1 blade servomotor modification

KARAKEÇİLİ 1 HPP: 6,55 MW, Tokat - Turkey | 2018

Employer: Hatko Enerji | Investor: Hatko Enerji

OPERATIONS: Installation

• Turbine and Generator Installation
• Installation and connection of auxiliary equipment (drainage, cooling water, compressor) cables (instrument, supply, control)
• Rotor Pole Coil Assemblies
• Stator Assembly
• LV–MV Cabling and Termination
• Diesel Generator,
• Main Power Transformer Assemblies
• Embedded piping & anchorage operations
• Draft Tube installation and welding
• Penstock installation and welding
• Spiral Case installation and welding
• Grounding/earthing operations
• Commissioning, Start-up Testing and Start-up operations.

ALPASLAN 2 DAM: 2x32 + 2x117 MW, Muş - Turkey | 2018

Employer: Alstom (Ge) | Investor: Energo PRO

OPERATIONS: Supervision

• Inspection and Preservation of Stator Coils , Stator Core Lamination plate, Rotor Rim Plates, Generator/Turbine Bearing , Shaft
• Inspection and Preservation of Turbine components

DEREKÖY HPP: 5,64 MW, Antalya - Turkey | 2018

Employer: Andritz France | Investor: Reis Grubu

OPERATIONS: Intervention

ESENTEPE HPP: 2x8 MW, Trabzon - Turkey | 2018

Employer: Gugler Austria | Investor: Bahser Enerji

OPERATIONS: Pre-Installation / Supervision

• Plant pre-installation supervision

CALA HPP: 2x8 MW, Artvin - Turkey | 2018

Employer: Global Hydro Austria | Investor: MZH Enerji Üretim

OPERATIONS: Installation

2 vertical axis Pelton type generators and auxiliary equipment belong to;
• Hydraulic Turbines, Collectors and Auxiliary Equipment
• Inlet Valve and Auxiliary Equipment
• Generators and Auxiliary Equipment
• Cooling Water System and Auxiliary Equipments (CWS)
• Mechanical Supervision and Installation of Turbine and Generator Instruments

KHAW HPP: 0,8 MW, Amman - Jordan | 2018

Employer: Andritz FranceFayat Energie Services International

OPERATIONS: Installation

• Hydraulic piping

ELBİZ REGULATOR AND HPP: 1x5,3 + 1x2,3 MW, Adana - Turkey | 2018

Employer: Hydrosem | Investor: Bulut Enerji

OPERATIONS: Installation

ÇAYALTI REGULATOR AND HPP: 11 MW, Zonguldak - Turkey | 2018

Employer: Andritz France | Investor: Reis Grubu

OPERATIONS: Intervention

• The reparation works for the broken pins of the wicket gate extension,
• Draft tube and other oil leakages fixed,
• Shaft seal leakage solved

INTERMEDIATE HPP: 1,2 MW, Amman - Jordan | 2018

Employer: Andritz FranceFayat Energie Services International

OPERATIONS: Installation

• Hydraulic piping
• Pelton type runner installation

KALECİK HPP: 26 MW, Artvin - Turkey | 2018

Employer: Andritz France | Investor: Nuryol Enerji

OPERATIONS: Intervention

• Change of the two leaking nozzles by spare ones

ÇALIKOBASI HPP: 8,84 MW, Giresun - Turkey | 2018

Employer: Andritz France | Investor: Akfen Enerji

OPERATIONS: Intervention / Supervision

• Hydraulic piping
• Runner installation
• Nozzle and runner alignment

KAVAK HPP: 12 MW, Artvin - Turkey | 2017-2018

Employer: Andritz France | Investor: MNG / Mapa İnşaat / Arhavi Elektrik Üretimi

OPERATIONS: Supervision

• 2 Horizontal Francis Turbine Installation supervision service

OMALA DAM AND HPP: 17 MW, Tokat - Turkey | 2017-2018

Employer: Neka / Adsel Elektrik Enerji | Investor: Neka / Adsel Elektrik Enerji / Yunhe

OPERATIONS: Installation

İSKENDERUN IRON & STEEL PLANT: 220 MW, Hatay - Turkey | 2017-2018

Employer: ODS Muhendislik | Investor: OYAK

OPERATIONS: Installation

• Installation of chimney sweeping mechanisms.

DEREKÖY HPP: 5,64 MW, Antalya - Turkey | 2017-2018

Employer: Andritz France | Investor: Reis Grubu

OPERATIONS: Intervention

DELİCE 1 HPP: 6,66 MW, Tokat - Turkey | 2017

Employer: Andritz France | Investor: Enerji 2023

OPERATIONS: Intervention

OKKAYASI REGULATOR AND ŞEHİTLİK HPP: 23 MW, Kahramanmaraş - Turkey | 2017

Employer: Andritz France | Investor: Okkayası Elektrik Üretim

OPERATIONS: Intervention

GÜMÜŞÖREN DAM AND HPP: 2x2,4 MW, Kayseri - Turkey | 2017

Employer: Global Hydro Austria | Investor: EÜAŞ

OPERATIONS: Installation / Supervision

• Mechanical erection services for Global Hydro Austria
• 2 x Horizontal axis Kaplan type turbine-generator installation and supervision

KÖPRÜBAŞI DAM AND HPP: 74 MW, Bolu - Turkey | 2017

Employer: Yüksel Enerji | Investor: Yüksel Enerji

OPERATIONS: Maintenance

• Annual maintenance work

KALECİK HPP: 2x12,9 MW, Artvin - Turkey | 2017

Employer: Andritz France | Investor: Nuryol Enerji

OPERATIONS: Installation

• Supervision for Andritz France and mechanical erection for Client
• Assembly of Pelton Type Turbines with 2x vertical force

SEMA HPP: 17 MW, Kırıkkale - Turkey | 2017

Employer: CG Enerji Elektrik | Investor: CG Enerji Elektrik

OPERATIONS: Maintenance

• Maintenance and repair works of power plant in operation

SIRAKONAKLAR HPP: 18 MW, Erzurum - Turkey | 2017

Employer: 2M Enerji | Investor: 2M Enerji

OPERATIONS: Maintenance

• Turbine maintenance works

EĞER HPP: 1,92 MW, Kütahya - Turkey | 2017

Employer: Eger Elektrik Üretim | Investor: Eger Elektrik Üretim

OPERATIONS: Maintenance (Over Haul)

• Butterfly valve water leaks control
• Elimination of leakage of cooling water system control
• Lubrication system leakage control.
• Governor system oil leak control
• Guide bearing and thrust bearing control
• Control of cavities in runner and wicket gate, cavitation studies
• Adjusting the wicket gate openings, eliminating misalignments
• Oil and gas control of turbine and generator
• Generator control
• Controls and changes of the brakes
• Warning coal control
• Shaft seal water leak control
• Control of all mechanical components

KOZDERE HPP: 9,27 MW, Antalya - Turkey | 2017

Employer: Ado Enerji | Investor: Ado Enerji

OPERATIONS: Maintenance

GÜNEŞLİ 2 REGULATOR AND HPP: 12 MW, Trabzon - Turkey | 2017

Employer: Bayraktar İnşaat | Investor: Bayraktar İnşaat

OPERATIONS: Maintenance (Over Haul)

• Over Haul maintenance works

YAZI HPP: 1,06 MW, Çankırı - Turkey | 2017

Employer: Küçükler Holding | Investor: Küçükler Holding

OPERATIONS: Maintenance

AZMAK VE KİRPİLİK HPP: 24 MW, Mersin - Turkey | 2017

Employer: BM Holding | Investor: BM Holding

OPERATIONS: Maintenance

OSMANCIK HPP: 9,02 MW, Amasya - Turkey | 2017

Employer: Rönesans Enerji | Investor: Rönesans Enerji

OPERATIONS: Maintenance

YUKARI KALEKÖY DAM AND HPP: 627 MW, Bingöl - Turkey | 2017

Employer: Cengiz Enerji | Investor: Cengiz Enerji

OPERATIONS: Consultancy

• Rotor rim heating and erection supervision and services

ŞAVŞAT HPP: 7,48 MW, Artvin - Turkey | 2016-2017

Employer: Andritz France | Investor: 2M Enerji

OPERATIONS: Supervision

• Supervision of Turbine and Generator Erection

MUTLULAR BIOMASS PP: 30 MW, Balıkesir - Turkey | 2016-2017

Employer: Mutlular Enerji | Investor: Mutlular Enerji

OPERATIONS: Maintenance

• Switchgear Tests (Relay, Transformer, Feeder)
• Hi-Pod Xlpe Dc-Ac 120 Kv Energy Tests
• Generator Ac Resisting Im Tests
• MV LV-DC Insulation Tests

ZİYARET HPP: 3,4 MW, Erzincan - Turkey | 2016-2017

Employer: Hidroen / IHB | Investor: Gökçeköy Elektrik Üretim

OPERATIONS: Supervision

• Supervision for Hidroen and IHB and electro-mechanical erection of all equipment
• Installation of LV - MV cells, internal requirement transformer, diesel generators, main power transformers
• High voltage tests
• AG-YG cabling and termination
• All electrical installations
• Pan assembly for power and control cables
• Installation of electrical-automation equipments and construction of internal connections.
• Xlpe cabling Shrinkage, pan assembly, Chamber installation, head construction and end connections
• OG - LV DC Line and Control Cable Drawings, assembly to ceiling, hood construction and end connections
• Grounding of all systems
• Installation of lightning rod installation
• Construction of lighting and installation works of powerhouse and end connections
• Construction of low current installations (fire alarm, telephone, data, camera) and terminal connections, except for commissioning works
• Installation and connection of auxiliary equipment (drainage, cooling water, compressor) cables (instrument, supply, control)
• Construction of cabling and connections for generator-turbine equipment (supervised)

KARAKEÇİLİ 1 HPP: 6,55 MW, Tokat - Turkey | 2016-2017

Employer: Hatko Enerji | Investor: Hatko Enerji

OPERATIONS: Consultancy

• Electromechanical and hydromechanical design control,
• Quality control,
• Electromechanical erection at site
• Turbine -Generator Manufacturing Controls
• Technical Document Preparation
• Feasibility Studies
• Power Plant, Regulator 1 Loading Pool Grounding Studies
• Spiralcase (Snail) Assembly and Resources

FAR-PLAS: Kocaeli - Turkey | 2017

Employer: Far-Plas | Investor: Far-Plas

OPERATIONS: Consultancy

• Technical electrical consultancy service

EMRE SPP: 4 MW, Ankara - Turkey | 2016-2017

Employer: Kaya Turizm | Investor: Kaya Turizm

OPERATIONS: Consultancy

• Feasibility Studies
• Energy Transfer Line Studies

ÜÇHARMANLAR HPP: 17 MW, Trabzon - Turkey | 2016

Employer: Ic İçtaş Enerji | Investor: IC İçtaş Enerji

OPERATIONS: Maintenance

• Cooling water system rehabilitation works

ÜÇHANLAR HPP: 11 MW, Trabzon - Turkey | 2016

Employer: Ic İçtaş Enerji | Investor: IC İçtaş Enerji

OPERATIONS: Maintenance

• Cooling water system rehabilitation works

KEMERÇAYIR HPP: 15 MW, Trabzon - Turkey | 2016

Employer: Ic İçtaş Enerji | Investor: IC İçtaş Enerji

OPERATIONS: Maintenance

• Cooling water system rehabilitation works

HAYGES ENERGY SPP: 6 MW, Kırıkkale - Turkey | 2016

Employer: Hayges Enerji | Investor: Hayges Enerji

OPERATIONS: Installation / Supervision

• Control and smooth pushing of the designs required for the installation of GES, making the missing designs,
• The establishment of the GES, the license required to be taken into operation, the coordination of the receipt of administrative affairs,
• Installation and assembly of inverters,
• Installation and assembly of solar cable,
• Connector assembly and installation,
• Design and installation of transformer substation
• Installation power transmission line, distribution centre, measurement cells, auto producer cell and other elements,
• Installation of network protection system with auto producer cell,
• Establishment of closed-circuit camera system
• Establishment of a data control and remote monitoring system,
• Field tests of all equipment in the plant

YUMRUTEPE HPP: 15 MW, Giresun - Turkey | 2016

Employer: Yumrutepe Enerji | Investor: Yumrutepe Enerji

OPERATIONS: Installation

• Horizontal francis type 3 unit turbine and generator mechanical ınstallation
• Governor piping and installation of equipment
• Installation of drainage and dewatering piping and equipments for all units
• Installation of low and high pressure piping systems for all units
• Inlet (Butterfly Valve) valve assembly
• Rotor shaft assemblies from shaft moveables (shaft + rotor carcass)

ERENKÖY HPP: 3x7,5 MW, Artvin - Turkey | 2016

Employer: Türkerler Holding | Investor: Türkerler Holding

OPERATIONS: Maintenance

• Horizontal francis turbine runner, generator assembly and re-assembly
• Damaged shaft seal labyrinth manufacturing
• Front and rear mirror replacement,
• Setting wicket gates

ÇAY REGULATOR AND HPP: 10 MW, Giresun - Turkey | 2015-2016

Employer: Martı Elektrik Üretim | Investor: Martı Elektrik Üretim

OPERATIONS: Maintenance

• Turbine -Generator installation and demounting
• Bedding
• Rotor Balance Setting
• Turbine Cavitation Studies

İKİLER HPP: 6,12 MW, Karabük - Turkey | 2015-2016

Employer: İskele Elektrik Üretim | Investor: İskele Elektrik Üretim

OPERATIONS: Consultancy

• Electro-Mechanical consultancy,
• Erection of all generator-turbine including supervision
• Turbine and Generator, project coordination for electromechanical and hydromechanical, coordination at site with civil group
• Commissioning works

ANGUTLU HPP: 23 MW, Giresun - Turkey | 2015

Employer: Türkerler Holding | Investor: Türkerler Holding

OPERATIONS: Maintenance

• Runner repair services

İKİZDERE HPP: 19 MW, Rize - Turkey | 2015

Employer: Zorlu Enerji | Investor: Zorlu Enerji

OPERATIONS: Maintenance

• Runner rehabilitation

TEPEKIŞLA DAM AND HPP: 2x34 + 4 MW, Tokat - Turkey | 2015

Employer: Alstom (Ge) | Investor: Sanko Holding / Ark Enerji

OPERATIONS: Installation

• Turbine and Generator Installation
• Installation and connection of auxiliary equipment (drainage, cooling water, compressor) cables (instrument, supply, control)
• Rotor Pole Coil Assemblies
• Stator Assembly
• LV and MV Cell Internal Requirement Transformers,
• Diesel Generator,
• Main Power Transformer Assemblies

ÇİLEHANE HPP: 7,2 MW, Tokat - Turkey | 2014-2015

Employer: NKD Elektrik Enerji | Investor: NKD Elektrik Enerji

OPERATIONS: Installation

• LV - MV Cells Installation
• Internal Requirement Transformer Installation
• Diesel Generator Installation
• Main Power Transformer Installation
• High Voltage Tests
• LV-HV Wiring and Termination
• All Electrical Installations

YEDİGÖZE SANİBEY DAM: 311 MW, Adana - Turkey | 2014

Employer: Sanko Enerji | Investor: Sanko Enerji

OPERATIONS: Maintenance

• Turbine Pull Balance Pipe Replacement

TOKAT SUÇATI HPP: 8,32 MW, Tokat - Turkey | 2013-2014

Employer: Artı Değer Enerji | Investor: Artı Değer Enerji

OPERATIONS: Maintenance

• Runner cavitation studies
• Turbine-generator maintenance
• Governor plc engine treatments
• Cooling oil tank maintenance
• Generator dc test works
• Rotor megger test works
• Transformer maintenance and cleaning
• Removal of circuit breaker faults

CEVHER 1 VE 2 HPP: 16 MW, Trabzon - Turkey | 2013

Employer: Elbi Enerji | Investor: Elbi Enerji

OPERATIONS: Maintenance

SEMA HPP: 17 MW, Kırıkkale - Turkey | 2013

Employer: CG Enerji Elektrik | Investor: CG Enerji Elektrik

OPERATIONS: Consultancy / Maintenance

Consultancy:
• All electromechanical and hydromechanical equipment maintenance services
• Cooling systems failure maintenance works
• Governor breakdown maintenance works
• Electrical - Automation - Scada

Maintenance:
• Flow measurement device instalation
• Snail sanding and paint processing

ÖZLÜCE HPP: 36 MW, Erzurum - Turkey | 2012-2013

Employer: Aksu Grup | Investor: Aksu Grup

OPERATIONS: Maintenance

• Pelton Turbine Runner Cavitation Studies,
• Disassemble Nozzles,
• Removal of Oil and Water Leaks

DOĞANKAYA HPP: 3x7,5 MW, Adıyaman - Turkey | 2012-2013

Employer: Gülsan Holding | Investor: Gülsan Holding

OPERATIONS: Maintenance

• Spiral case assembly and welding,
• Turbine-generator installation,
• Oil, air and cooling water piping,
• Rotor pole coil works,
• High voltage tests,
• Low voltage and medium voltage cubicles,
• Auxiliary transformer,
• Ddiesel generator,
• Main power transformer installation,
• Low and high voltage cabling and termination,
• Installation of all electrical systems.

DOĞANKAYA HPP: 3x7,5 MW, Adıyaman - Turkey | 2011-2012

Employer: Gülsan Holding | Investor: Gülsan Holding

OPERATIONS: Installation

• Turbine and Generator Installation
• Installation and connection of auxiliary equipment (drainage, cooling water, compressor) cables (instrument, supply, control)
• Rotor Pole Coil Assemblies
• Stator Assembly
• LV–MV Cabling and Termination
• Diesel Generator,
• Main Power Transformer Assemblies
• Embedded piping & anchorage operations
• Draft Tube installation and welding
• Penstock installation and welding
• Spiral Case installation and welding
• Grounding/earthing operations
• Commissioning, Start-up Testing and Start-up operations.

MİDİLLİ HPP: 3x10 + 1,5 MW, Amasya - Turkey | 2011-2012

Employer: Masat Enerji | Investor: Bereket Enerji / Goldman Sachs

OPERATIONS: Installation

• Turbine and Generator Installation
• Installation and connection of auxiliary equipment (drainage, cooling water, compressor) cables (instrument, supply, control)
• Rotor Pole Coil Assemblies
• Stator Assembly
• LV–MV Cabling and Termination
• Diesel Generator,
• Main Power Transformer Assemblies
• Embedded piping & anchorage operations
• Draft Tube installation and welding
• Penstock installation and welding
• Spiral Case installation and welding
• Grounding/earthing operations
• Commissioning, Start-up Testing and Start-up operations.

ÇILDIR HPP: 3x5,12 MW, Kars - Turkey | 2011

Employer: Zorlu Enerji | Investor: Zorlu Enerji

OPERATIONS: Maintenance

• Stator coil changes,
• Coil drying,
• Testing and start-up operations.

ERENKÖY HPP: 3x7,5 MW, Artvin - Turkey | 2011

Employer: Türkerler Holding | Investor: Türkerler Holding

OPERATIONS: Maintenance

• Wicked gates cavitations repairs,
• Rotor cavitations repairs,
• Turbine cover and ring repairs

KALE HPP: 29 MW, Amasya - Turkey | 2010-2012

Employer: Rönesans Enerji | Investor: Rönesans Enerji

OPERATIONS: Maintenance

• Kaplan Type runner cavitation processes
• Rotor insulation tests

PAMİR 1-2 HPP: 46 MW, Khorog - Tajikistan | 2010-2011

Employer: Pamir Energy | Investor: Pamir Energy

OPERATIONS: Maintenance

• Adjustment wicket gates,
• Rotor, head cover, turbine shaft manufacturing,
• Cooling water system renewal,
• White metal bearing installation,
• Stator coil manufacturing,
• Disassembly and assembly.
• Inlet valve rehabilitation,
• Pamir 2 white metal coil rehabilitation.

ÇAMLICA 1 HPP: 3x30 MW, Kayseri - Turkey | 2010

Employer: Ayen Enerji | Investor: EÜAŞ

OPERATIONS: Maintenance

• Generator rotor and top bridge disassembly and assembly,
• Coil renewal,
• High voltage tests and start-up

BEYKÖY HPP: 3x6,08 MW, Eskişehir - Turkey | 2010

Employer: Zorlu Enerji | Investor: Zorlu Enerji

OPERATIONS: Maintenance

• Generator rotor and top bridge disassembly and assembly,
• Coil renewal,
• High voltage tests and start-up

YAVUZ HPP: 3x7,5 MW, Amasya - Turkey | 2008-2010

Employer: Masat Enerji | Investor: Bereket Enerji / Goldman Sachs

OPERATIONS: Installation

• Turbine and Generator Installation
• Installation and connection of auxiliary equipment (drainage, cooling water, compressor) cables (instrument, supply, control)
• Rotor Pole Coil Assemblies
• LV–MV Cabling and Termination
• Diesel Generator,
• Main Power Transformer Assemblies
• Spiral Case installation and welding
• Grounding/earthing operations
• Commissioning, Start-up Testing and Start-up operations.

YALNIZCA HPP: 14 MW, Karabük - Turkey | 2008-2009

Employer: Rönesans Enerji | Investor: Rönesans Enerji

OPERATIONS: Maintenance

• Kaplan Type runner Cavitation Processes,
• Turbine Disassembly,
• Shaftseal Wear Ring Demounting

CİNDERE DAM AND HPP: 3x10,5 MW, Denizli - Turkey | 2008-2009

Employer: Entek Enerji | Investor: Entek Enerji

OPERATIONS: Maintenance

• Spiral case erection and Welding operations,
• Turbine generator mechanical installation,
• Rotor pole coil works,
• Oil, water, cooling water piping.

IŞIKLAR (VİSERA) HPP: 2x0,65 MW, Trabzon - Turkey | 2006

Employer: Demistaş / EÜAŞ | Investor: Metek Hidro Enerji

OPERATIONS: Maintenance

• Renovation, disassembly & assembly of Stator & Rotor coils,
• Coil drying,
• Testing and start-up operations.

OYMAPINAR DAM AND HPP: 4x135 MW, Antalya - Turkey | 2006

Employer: Cengiz Enerji | Investor: Cengiz Enerji

OPERATIONS: Maintenance

• Stator coil drying,
• Testing and start-up operations.

ENGİL HPP: 3x1,912 MW, Van - Turkey | 2004

Employer: EÜAŞ | Investor: Haliç Elektrik Üretim

OPERATIONS: Maintenance

• Generator coil changes,
• Coil drying,
• Testing and start-up operations.
• Rotor pole coil changes

ALAÇATI ARES WPP: 12x0,6 MW, İzmir - Turkey | 2003-2004

Employer: Ares Enerji | Investor: Ares Enerji

OPERATIONS: Maintenance

• Maintenance and test of 12 generators,
• Renewal of coils of 12 generators.

KOVADA 1 HPP: 2x27 MW, Isparta - Turkey | 2003

Employer: Damlapınar Energy / EÜAŞ | Investor: Batıçim Enerji

OPERATIONS: Maintenance

• Manufacturing and installation of 288 ROEBEL Bar type generator stators & 10 Rotor Pole Coils,
• Start-up after drying

SEYHAN HPP: 27 MW, Adana - Turkey | 1998

Employer: Çukurova Elektrik | Investor: EÜAŞ

OPERATIONS: Maintenance

• 60 ROEBEL BAR Type Stator Coil Manufacturing,
• Installation and start-up.

MET A.Ş.: 1,5 + 15 MW, Konya - Turkey | 1996-2007

Employer: EÜAŞ | Investor: EÜAŞ

OPERATIONS: Maintenance

• Renovation of stators and rotors of generators between 1.5 MVA to 15 MVA

GÖKÇEKAYA DAM AND HPP: 3x95 MW, Eskişehir - Turkey | 1995-1996

Employer: EÜAŞ | Investor: EÜAŞ

OPERATIONS: Maintenance

• Cavitation and Rotor coil isolation operations

TUNÇBİLEK TERMİK SANTRALİ: 3x150 MW, Kütahya - Turkey | 1995

Employer: EÜAŞ | Investor: Çelikler Enerji

OPERATIONS: Maintenance

• Change of 120 expansion joints

HOŞAP HPP: 3,5 MW, Van - Turkey | 1990-2000

Employer: EÜAŞ | Investor: Haliç Elektrik Üretim

OPERATIONS: Maintenance

• Generator coil renewal,
• Rotor pole coil renewal,
• White metal bearing molding

KEBAN DAM AND HPP: 8x202 MW, Siemens – AEG, Elazığ - Turkey | 1990

Employer: EÜAŞ | Investor: EÜAŞ

OPERATIONS: Maintenance

• Disassembly and installation of rotor and upper bracket,
• Change of older stator coil with locally manufactured parts,
• Coils drying and start-up operations.

OYMAPINAR DAM AND HPP: 4x135 MW, Antalya - Turkey | 1988

Employer: Cengiz Enerji | Investor: Cengiz Enerji

OPERATIONS: Long Term Follow Ups

• Disassembly and installation of rotor and upper bracket,
• Change of older stator coil with locally manufactured parts,
• Coils drying and start-up operations.

HİRFANLI DAM AND HPP: 128 MW, Kırşehir - Turkey | 1980-1983

Employer: EÜAŞ | Investor: EÜAŞ

OPERATIONS: Long Term Follow Ups

• Installation of locally manufactured turbine generator coil and Rotor pole coils.
• Preparation and installation,
• Commissioning of rotor and stator lamination coils

SARIYAR HASAN POLATKAN HPP: 160 MW, Ankara - Turkey | 1979-1990

Employer: EÜAŞ | Investor: EÜAŞ

OPERATIONS: Long Term Follow Ups

• Disassembly and installation of rotor and upper bracket,
• Change of older stator coil with locally manufactured parts,
• Stator coil drying,
• Testing and start-up operations.

HOŞAP HPP: 3,5 MW, Van - Turkey | 1975-1990

Employer: EÜAŞ | Investor: Haliç Elektrik Üretim

OPERATIONS: Long Term Follow Ups

• Renewal of generator coil,
• Change of rotor pole coil,
• White metal bearing installations

Makelsan Electric-Energy with our expert staff with years of experience and as long;for a beautiful future, we're doing what we know best.